[Procedure name] | Notification of Operational Suspension or Discontinuance of an Integrated Customs Area |
(Procedure for a customs (bonded) area) |
|
|
[ | Summary] |
- | Procedure required when a juridical person or a freight manager, who has the permit of an integrated customs area, intends to suspend or discontinue its operation within the permission period |
|
[ | Bases for procedures] |
- | Article 62-15 (application of Article 46) of the Customs Law |
- | Article 51 (application of Article 39, Paragraph 1) of the Cabinet Order for Enforcement of the Customs Law |
|
[ | Subjects to procedure] |
- | Juridical person which has the permit of an integrated customs area or a freight manager |
|
[ | Time of submission] |
- | Submit a notification as early as possible so that you could suspend or discontinue the operation of your integrated customs area or freight facility within the period of permission. |
|
[ | Method of submission] |
- | Prepare your notification and submit it to the customs office stated below. |
|
[ | Fee] |
- | There is no fee for notification. |
|
[ | Documents to be attached and number of copies] |
- | No documents to be attached required. |
|
|
[ | Submitted to] |
- | Submit your notification to a hozei section official of the customs office having jurisdiction over the area where the said integrated customs area is located. |
|
[ | Reception time] |
- | Office hours of customs (8:30 a.m. through 5:00 p.m. except on holidays for the administrative agencies) |
|
[ | Consultation service] |
- | For information, ask a customs counselor or the customs office that processes your application. |
|
[ | Submission standard] |
- | Foreign goods must not be left in the integrated customs area concerned or the freight facility. |
|
[ | Standard processing time] |
| |
|
|
[ | Remarks] |
- | Customs may ask the notifier to submit a list of foreign goods if they are left in the integrated customs area or freight facility which is scheduled to be suspended or discontinued. |
- | When the notifier, who submitted a notification of suspension of operation, intends to resume operation, he is required to go through a resumption procedure for operation. |
|